Current Projects

PAR 1117 DSS Conveyor System Rehabilitation

Rehabilitation of the Conveyor System

Owner:  Metro Wastewater  | Engineer:  Bates Engineering

Project Schedule: 2/2010 - 10/2010 | Progress: 5% | Value: $936,183

 

 

 

Crested Butte Wastewater Treatment Facility Improvements

Construction of a new Clarifier and new Clarifier Structure

Owner:  City of Crested Butte  | Engineer:  HDR

Project Schedule: 5/2010-2/2011 | Progress: 15% | Value: $1,361,615

 

Specifications and Drawings

 

 

 

Ammonia & Nutrient Removal Section 4 Lift Station

Upgrade to four wastewater lift stations for the City of Pueblo, including pipe replacement and pipe coating

Owner:  City of Pueblo  | Engineer:  Black & Veatch

Project Schedule: 2/2010 - 10/2010 | Progress: 5% | Value: $608,000

 

Specifications and Drawings

 

Greeley Aeration System Improvements

Replacement of blowers and air piping in existing blower building and installation of new diffuser system in aeration basins, with associated building modifications and landscaping.

Owner:  City of Greeley | Engineer:  Brown and Caldwell

Project Schedule: 2/2010 - 10/2010 | Progress: 20% | Value: $2,324,970

 

Specifications and Drawings

 

 

 

Andrews WST

2.0 MG waster storage tank repairs, including earthwork and installation of new pipeline.

Owner:  Left Hand Water | Engineer:  Bates Engineering

Project Schedule: 2/2010-7/2010 | Progress: 95% | Value: $284,401

 

 

Specifications and Drawings

 

 

Rocky Ford

Upgrade if the UV Components for the Water Treatment Plant

Owner:  City of Rocky Ford | Engineer:  TST Inc.

Project Schedule: 2/2010-10/2010 | Progress: 68% | Value: $1,984,151

 

Specifications and Drawings

 

 

 

Cold Springs

Installation of membrane water treatment system including hypochlorite feed system and the associated building for the feed system.

Owner:  Colorado City | Engineer:  Malcolm Pierne

Project Schedule: 9/2009-5-2010 | Progress: 98% | Value: $1,025,565

 

Specifications and Drawings

 

Lamar WWTP

Construction of a wetwell/drywell wastewater lift station and headworks facility.

Owner:  City of Lamar | Engineer:  The Engineering Company

Project Schedule: 6/2010 - 6/2011  | Progress: 5% | Value:  $2,106,331

 

Specifications and Drawings

 

La Junta WST and Pump Station

Removal and replacement of water storage tank and installation of new pump stations.

Owner:  City of La Junta | Engineer:  The Engineering Company

Project Schedule: 9/2009-8/2010 | Progress: 98% | Value: $1,834,152 

 

Specifications and Drawings

 

 

Boyd Lake PAC Silo

Installation of powdered activated carbon silo and transfer system with associated piping and electrical modification.

Owner:  City of Greeley | Engineer:  City of Greeley

Project Schedule: 10/2009-6/2010  | Progress: 98% | Value:  $192,870

 

Specifications and Drawings

 Adams Street Lift Station

 

Installation of sewage grinder, construction of new wetwell, lift station and emergency generator.

 

Owner:  City of Laramie | Engineer:  The Engineering Company

Project Schedule: 7/2009-7/2010 | Progress: 95% | Value:  $729,500

 

Specifications and Drawings

Cat Pump Station and Miller Reservoir

Construction of a new pump station, intake and outfall structure and

rehabilitation of reservoir lining for the Cat reservoir. 

Upgrade electrical and instrumentation equipment at existing pump station at Miller reservoir.

 

Owner:  Denver Water | Engineer:  Denver Water

Project Schedule: 9/2008 - 6/2009 | Progress: 10% | Value:  $3,536,088

South Adams County Lift Station No. 2

Addition to an existing lift station, including building construction and furnishing

and installing 5 new 1,100 gpm wastewater pumps

Owner:  South Adams County Water and Sanitation District | Engineer:  Black and Veatch

Project Schedule: 4/2009-11/2009 | Progress: 0% | Value:  $1,227,965

Specifications and Drawings

Reuter Hess Dam and Reservoir Enlargement

 

Mechanical installation for dam and reservoir

Owner:  Parker Water and Sanitation | Engineer:  RJH Consultants | General Contractor:  Ames Construction

Project Schedule: 3/2009 - 9/2009 | Progress: 0% | Value:  $897,260