Current Projects

Carter Lake Hydroelectric Plant

Construction of power house facility for two 1500KVA turbine generators

Owner:  Northern Water Hydropower Water Activity Enterprise  | Engineer:  Black & Veatch

Project Schedule: 8/2011-6/2012 | Progress: 2% | Value: $1,774,669

 

Bellvue Drying Beds

Installation of a large asphalt drying bed for sludge containment

Owner:  City of Greeley  | Engineer:  Smith Geotechnical Engineering Consultants

Project Schedule: 8/2011-12/2011 | Progress: 1% | Value: $832,600

 

 

CDOC WWTP Pretreatment Facilities

Construction of pre-treatment facility structures and screening handling equipment at the Mackenzie and Brewster outfall structures.

Owner:  Colorado Department of Correction  | Engineer:  Richard P Arber

Project Schedule: 3/2011-11/2011 | Progress: 85% | Value: $1,342,272

 

Milton Seaman Reservoir Outlet Maintenance

Installation of a trash rack structure and replacement of existing hydraulic gate.

Owner:  City of Greeley  | Engineer:  URS

Project Schedule: 2/2011-3/2012 | Progress: 2% | Value: $1,150,530

 

 

Greeley Lift Station 13 Box Culvert

Construction of a lift station and a box culvert

Owner:  City of Greeley  | Engineer:  KBN & AVI

Project Schedule: 6/2011-8/2011 | Progress: 0% | Value: $790,000

 

Specifications and Drawings

 

Benkelman WTP

Construction of a water treatment facility

Owner:  City of Benkelman  | Engineer:  Baseline Engineers

Project Schedule: 4/2011 - 1/2012 | Progress: 0% | Value: $921,000

 

Specifications and Drawings

 

Nederland

Construction of a wastewater treatment plant

Owner:  Nederland | Engineer:  Frachetti Engineering

Project Schedule: 3/2010-3/2011 | Progress: 0% | Value: $3.8 Million

 

 

Greeley Aeration System Improvements

Replacement of blowers and air piping in existing blower building and installation of new diffuser system in aeration basins, with associated building modifications and landscaping.

Owner:  City of Greeley | Engineer:  Brown and Caldwell

Project Schedule: 2/2010 - 10/2010 | Progress: 20% | Value: $2,324,970

 

Specifications and Drawings