Principal Profile

Michael Pelphrey

President

 

Kipp Ketterer

Vice President

 

Robert MacTaggart

Vice President

 

Carl Olivas

Vice President

Broomfield Water Treatment Plant

Value:  $9.3 million      

Contract Time:  15 months

Project Manager:  Michael Pelphrey

Project Superintendent:  Kipp Ketterer

Area Superintendent:  Robert MacTaggart ($4.5 million portion of work)

Existing water treatment plant expansion including new pretreatment basins, settling filters, chlorine contact basin, backwash separation basins, high service pumps, backwash recycle pumps, interior and buried process piping & plumbing, electrical, control, and landscaping.

Casper Water Treatment Plant

 

Value:  $31.1 million

Contract Time:  15 months

Project Manager:  Michael Pelphrey

Project Superintendent:  Kipp Ketterer ($12 million portion of work)

Assistant Superintendent:  Robert MacTaggart ($12 million portion of work)

Existing water treatment facility expansion and new construction, including ozone disinfection, conversion of existing sedimentation basins to high rate coagulation clarification (Actiflo) process, chemical feed system, polymer injection, filter rehabilitation, conversion of existing sedimentation basins to a chemical feed and storage building, high service pumps, interior and buried process piping & plumbing, administration annex, new laboratory and computer control room, electrical, programmable logic control system, landscaping.

Laramie Wastewater Treatment Plant

Value:  $10.6 million

Contract Time:  18 months

Project Manager:  Michael Pelphrey

Assistant Superintendent:  Kipp Ketterer

Head Foreman:  Robert MacTaggart

New wastewater treatment plant construction, including solids screening, aeration basins and equipment, clarification basins and equipment, aerobic digester basins and equipment, ultraviolet disinfection, office annex, new building construction, programmable logic control system, plus all associated process piping, pumping, plumbing, electrical, landscaping.

Laramie Wastewater Treatment Plant

Value:  $2.6 million      

Contract Time:  8 months

Project Manager:  Michael Pelphrey

Project Superintendent:  Kipp Ketterer

Assistant Superintendent:  Robert MacTaggart

New wastewater treatment plant facilities, including solids handling pumps, belt press solids handling, polymer systems, waste conveying systems, solids drying beds, plus all associated piping, pumping, plumbing, electrical, and facilities buildings.

Grand County 1.0 MG Tank

Value:  $1.4 million

Contract Time:  6 months (excludes 4 month winter shutdown)

Project Manager:  Michael Pelphrey

 New 1.0MG concrete storage tank, plus associated piping and landscaping.

City of Lafayette Water Treatment Plant

Value:  $2.2 million

Contract Time:  10 months                   

Superintendent:  Kipp Ketterer

Expansion of existing water treatment plant including clarification basins, new pumping systems, sludge lagoons, process piping and plumbing, electrical, and landscaping.

City of Arvada Water Treatment Plant

Value:  $7.3 million

Contract Time:  15 months

Area Superintendent:  Kipp Ketterer ($2.0 million portion of the work)

New water treatment plant construction.

City of Ft. Morgan Waste Water Treatment Plant

Value:  $8.3 million

Contract Time:  16 months

Project Engineer:  Michael Pelphrey

Field Engineer:  Kipp Ketterer

New wastewater treatment plant construction.

City of Ft. Collins Waste Water Treatment Plant

 

Value:  $5 million (Design-build)

Contract Time:  12 months

Project Engineer:  Michael Pelphrey

Expansion of existing wastewater treatment plant, including new clarifier construction and existing clarifier rehabilitation, new intake structure and screening, new odor control facilities, new landscaping pond, plus all associated process piping, plumbing, electrical, control, and landscaping.

City of Ft. Collins Water Treatment Plant

Value:  $6 million (Design-build)                      

Contract Time:  3 years

Project Engineer:  Michael Pelphrey

Expansion of existing water treatment plant, including new chlorine systems, new sludge ponds, and new filters.